Short-term Flow Tests on Test Well for Geothermal Power Generation in the Oyasu region
October 4, 2018
Project
Mitsui Oil Exploration Co., Ltd. ("MOECO") has announced that it is being conducted short-term flow tests to gauge the capacity of a test well from 28th September to 18th October (planned). It has drilled in the Oyasu region of Akita Prefecture, Japan in partnership with Idemitsu Kosan Co., Ltd. and INPEX CORPORATION with which it has jointly pursued commercialization studies on geothermal power generation since 2011.
1. Details and objectives
The flow tests are being conducted on the test well A-1 and A-2 , which were drilled from May to September in this year. These wells will be evaluated their production capacity through 1-2 weeks continuous flow on the same size well as actual production well. Through these experiments, the companies verify details concerning well production capacity (volume of steam), underground temperatures, chemical composition of geothermal fluids, water permeability in the vicinity of the well, and other matters.
2. Overview of studies to date
(1) Stage 1: Completed in FY2011
Superficial surveys (ground-level geological surveys, gravitational exploration, electromagnetic exploration, etc.)
(2) Stage 2: Completed in FY2017
(i) Drilling survey, building roads for equipment transportation, etc.
Drilling exploratory wells* to study geological structures, underground temperatures and water permeability
* Exploratory well: Wells drilled to study underground structures and geothermal reservoir conditions in the initial stage of the study
(ii) Hot spring monitoring survey
Monitoring hot spring temperatures, yields, and chemical composition at nearby hot spring wells
3. Future schedule
MOECO and its partners plan to conduct the third stage of studies (including production and injection experiments, assessment of reservoir capacity and environmental surveys, etc.) from FY2018 to FY2021.
Short-term Flow Tests of Test Well